Safe Pre-commissioning commissioning of ammonia urea fertiliser plant
Ammonia – Urea fertiliser plant
possess high hazards due to handling and processing hazardous chemicals
including Natural gas, ammonia, hydrogen, carbon monoxide, chlorine, etc and
critical process parameters such as high pressure and temperature.
Safety of peoples, machines and environment are the key factors for successful plant commissioning. No commissioning can be considered a success if not done safely.
Commissioning of ammonia urea fertiliser plant |
Safe Pre-commissioning commissioning of ammonia urea fertiliser plant
First element of pre-commissioning
and commissioning is planning to commission of any facility safely and
in time. In this stage, organizational chart with roles and responsibilities of
all members of commissioning team are framed out. Decide all different types
of checklists i.e.
structure, piping, mechanical, electrical, instrumentation, etc and develop
operating manual.
Planning must be done along
with licensors, critical vendors and client so that their team should join the
commissioning activities on site.
Ensure advance planning of
material requirement. Material like blinds, split pieces, hoses, steam blowing
equipment, toolbox/ kit, etc my requires during pre-commissioning and
commissioning activities.
Scope of pre-commissioning and commissioning - Ammonia Urea fertiliser plant
Detail scope of pre-commissioning
and commissioning of Ammonia Urea fertiliser plant may include main
production plants such as ammonia plant, ammonia storage, Urea plant and Urea product
handling. Utilities includes raw water facility, water
treatment plant, cross country pipeline,
Fire water facility, power plant, heat recovery system, nitrogen plant, cooling
towers, Effluent treatment plant and rail wagon facility, etc.
Sequence of pre-commissioning and commissioning activities - ammonia urea plant
Below sequence is
recommended for ammonia urea plant pre-commissioning and commissioning activities
based on its priorities.
- Power and control system i.e. electrical substations, central control center, building power, etc.
- DCS and PLC systems and instrumentation
- Row water and firefighting systems
- Effluent treatment systems
- Chemical sewer systems and neutralization pits
- Service water, potable water and cooling water systems
- Instrument air, plant air and air regeneration systems
- Water treatment systems.
- DM plant
- Boiler water system
- The nitrogen system
- Flare system
- Plant safety equipment and fire and gas detection
- Fuel gas system
- Flushing oil system
- Boiler systems with steam and condensate networks
- Feed, ammonia storage and product handling systems
- All the process units and systems, etc.
Planning for Pre - commissioning activities – Ammonia Urea plant
Formation of Work Packages
The entire facility should be subdivided
into the work packages to determine the detail activities, skill and expertise
requirement, estimate for effort and duration for particular activity, its
scheduling, budget involved, and risk involved well in advance before starting
commissioning of plant. This will help
to determine the interlinking of operating systems, status of operating systems
completion, formation of loops which can be easily controlled and monitored,
etc.
Work
packages can be form by constituting the team of
experts from each functional area with a process leader. Roles and
responsibilities of each members must be identified and well communicated.
Leader must ensure the resources and close monitoring.
Identify the different loops
and check for an individual loop with respect to P&ID. Checking may include
the piping, valves and other instrument items, the support system, the
tightness for nuts and bolts, the gaskets, the blinds and temporary blind
removal along with blind register, the hydro/pneumatic test reports, flushing
and cleaning reports, insulation and painting reports.
Whatever the shortcomings or
pending point observations should be incorporated in “punch list” for
rectification. Punch list must be signed off and submit the status of
completion before handing over for commissioning.
Always maintain vendor
instruction file to document information or instructions received from
licensor/ vendors/ manufactures which may be readily retrieved by plant
commissioning team.
Prerequisite
Health Safety and Environment.
All personnel must be trained
to operate facility safely in accordance with the safety standards and
procedures.
The prime consideration in
plant operation and maintenance is assumed to be safety of personnel.
Detailed safety instruction
including Dos and Don’ts and procedures must be prepared, approved and
communicated to concerns.
Hazards should be identified,
and necessary risk mitigation measures should be provided.
Safety procedures should be
developed taking into account of rules and regulations.
Detailed fire precautions and first aid procedures should be developed
- Work permit – to control critical work, maintenance, repair other work of a hazardous or potentially hazardous nature.
- Personnel protection equipment.
- Training of all working personals.
- Plant maintenance
- Safety equipment
MSDS must be made available for
all hazardous chemicals.
Laboratory
Sometime hot commissioning and
initial start-up are planned at once, in such case, before the commissioning of
plant and initial start-up
- Analytical laboratory should be ready with chemicals and instrument.
- All equipment, chemicals and analytical manual are available.
- Laboratory is sufficiently staffed with experienced workers.
Workshop
Sometime hot commissioning and
initial start-up are planned at once, in such case, before the commissioning of
plant and initial start-up
- Mechanical/Electrical/Instrumentation workshop should be ready.
- All equipment, tools & tackles should be available.
- Workshop is sufficiently staffed with experienced workers.
Communication
and Public Address System
Check for completeness of
Public address system in all respect.
Recommended Task for pre-commissioning of fertiliser plant
Here are the recommended tasks
should be performed during the pre-commissioning and commissioning of ammonia
Urea plant.
Punch point Inspections and record
Commissioning team must inspect
the systems and subsystems to verify whether the specified materials/ items
have been installed in the facility according to drawings, specifications and
project intend. Verify the documents and maintain the record of verification.
The facility inspection can be
performed by using standard checklist as approved by commissioning team leader.
Note down any exceptions on a separate work order list or punch list with
roles, responsibility and target date for correction.
There may be need of special
inspections, such as those required by the insurance or governmental agencies
(Statutory Requirements), it must be coordinated by experts.
Lubricants Management
Prepare a list of lubricants
used for different machines recommended by manufacture and get it approved by
in-charge.
Ensure the availability of
desired lubricants.
Check for heating/cooling and
online clarification of lubricants.
Flush the system and initial
charge the lubricants.
All flushing oil should be
disposed out as per procedure.
Maintain lubrication after
initial charge.
Removal of rust preventives substances
Most of the rust preventives
and oil used to protect the equipment from rust during the construction period
may harmful to process operation. These oil / rust preventives must be removed
completely before equipment take into operation. Record should be maintained.
Packing and seals Management
Ensure the correct installation
of mechanical seals and accessories, as required.
Permanent packing and
accessories may be requiring at certain equipment.
Adjust and if requires, replace
mechanical seals, packing, accessories and other required items during
commissioning period.
Remove temporary bracing/ supports
Remove all temporary supports, bracing or other foreign
objects that were used for packing or to prevent damages during shipping,
storage and erection of vessels, ducts, piping, transformer, machinery or other
equipment.
Inspect the equipment and installation thoroughly and repair
any damage.
Check rotation and alignment of rotary equipment
Before connecting to the
driver, all rotary equipment/ machinery must be checked for correct direction
of rotation and for freedom of moving parts.
According to the manufacturer’s
tolerances data, perform cold alignment and maintain record.
Ensure hot alignment as
applicable according to manufacture guideline.
If need any doweling, perform
it according to equipment data sheet and manufacturer guideline.
OEM representative must be
involved to witness installation and pre-commissioning of critical and large equipment/
machines.
Tie-ins at unit limits
Inspect the installation as per
P&ID and prepare all the system and subsystem for safe tie-ins.
According to specification,
arrange for obtaining approval and making the necessary tie-ins at the unit
limits/ battery limit.
Maintain blind register and use
P&ID for marking the blinding/ deblending requirement. Remove blinds, seals,
and so forth as required.
Leak and pressure testing
Prepare detail schedule of
non-operating field leak/ pressure test for piping and field fabricated
equipment.
Decide the requirement of cold
or hot commissioning.
Decide whether any special
media required for test purposes.
Conduct all tests in accordance
with all applicable codes, specifications, regulations and the OEM instructions.
Pre-commissioning team must witness
the tests and maintain the records.
All test media used for leak/
pressure tests must be disposed out in accordance with the owner’s
instructions.
Ensure the operational
tightness tests is carried out for all identified system and subsystem with
equipment and fittings.
Use of temporary screens, strainers, and blinds
For successful flushing
activity, identify the needs for temporary screens, strainers and blinds.
Install all required temporary
strainers/screens/blinds and ensure cleaning of strainers during circulation.
Remove the temporary strainers
when system is adequately cleaned.
There may require providing
some blinds or to remove all blinds for flushing.
Maintain the blind register to
record the data for providing, installing and removing all blinds required for
isolation.
Flushing and chemical / mechanical cleaning
Identify the system and
subsystem for flushing or cleaning by chemical or mechanical means.
Identify the system or
subsystem for flushing/ cleaning by using permanently installed equipment or by
portable equipment.
Decide the acceptable flushing
media for particular system/ subsystem.
Conduct all flushing, blowing,
and chemical/mechanical cleaning operations with due care and maintaining the
safety system where such operation can be accomplished without using
permanently installed equipment.
To obtain proper line
velocities, flushing and blowing operations can be performed by using
permanently installed equipment.
Follow client’s guidelines/
operating procedures for safe disposal of all the cleaning/ flushing media used.
Check system for free of trash
and construction debris and maintain records.
Pressure / vacuum safety relief devices
All safety relief devices are
critical items and must be inspected, tested and installed properly as per
specification.
List out all the safety relief
devices with record such as pressure settings data, type of SRV, material of
construction, testing date and due date, etc.
Test and adjust all safety
relief devices and seals wherever necessary or desirable.
Install all devices safely after
testing, adjusting, and tightening and maintain record.
Purging operation by inert media
Ensure the safe and secured
connections for purging operation.
Decide the suitable purge
material and conduct necessary purge operation safely with permit to work.
Perform the work according to
manufacture guideline and follow standard operating procedures with caution
boards.
Dry out the facility
To prevent contamination of
catalyst, operating fluid or materials, ensure proper ‘dry out’ operation of system,
subsystem and equipment.
Identify the needs of portable
or fixed equipment for Dry out process.
All equipment must be
inspected, tested and certified for dry out systems for refractories, and
linings when drying operation is to be accomplished with temporary facilities.
Ensure safety and follow
standard operating procedures for drying operation accomplished by means of
permanently installed equipment.
Housekeeping
After mechanical completion of
construction work, maintain adequate housekeeping practices for safe pre-commissioning
or commissioning operation.
Remove excess material,
temporary facilities, scaffolding, etc and perform rough sweep or rake the area.
Pick up the trash and dispose it safely.
Perform washing or further
clean-up if required.
Commissioning activities – Ammonia Urea plant
After completion of inspection,
testing, alignment, flushing, purging, drying, closure of punch points, etc.
proceed for commissioning activities.
Once finished the pre-commissioning
activities, protect equipment from normal weather conditions, corrosion, or
damage. Ensure the availability of all-important spares and be prepared for
other emergency maintenance/ repair job predicted during commissioning
activities.
Maintenance tools and spares
Once pre-commissioning is
completed, review the list of maintenance spare parts specially gaskets, valves,
etc as recommended by the manufacturers for commissioning activities.
Ensure the availability of
special tools such as non-sparking tools to attend the leakages of flammable
gases.
Maintain adequate spare parts
and supplies.
Ensure the availability of
trained and qualified technicians to perform the emergency repair or
maintenance job.
Ensure availability of special
PPEs including chemical suits, respirators, electric arc / flash resistance
suit, etc.
Work Environment Survey
Conduct individual equipment
noise surveys, as required by the occupational safety and health administration
or the client specification.
Conduct survey for illumination
level.
Maintain record.
Commissioning activities/ process – Ammonia Urea Plant
Some time pre-commissioning and
commissioning activities can be performed simultaneously. After ensuring the
closeup of punch points, commissioning activities can be start in presence of
critical vendors, licensors and client.
Commissioning of Electrical Systems
Ensure proper earthing system
and witness tests.
Perform insulation tests on all
wiring except lighting wiring using a Mega ohm meter.
Insulation tests on motor and
transformer windings should be done from phase to phase and phase to ground.
Perform grounding system tests
to determine the continuity of connections and the value of resistance to
ground.
Arrange to get local electrical
inspector’s approval according to local or national laws.
Perform breakdown tests on oil
samples from oil insulated transformers larger than 100KV.
Perform trials and adjustments
on all switchgear, motor control equipment, and generators.
Test and set switchgear and
circuit breaker relays for proper coordination.
Energize all substations with
approval of the client after completion of all tests and ensuring the
availability of firefighting systems/ fire extinguishers.
Check for phase sequence,
polarity, and motor rotations.
Check installation of emergency
power and lighting systems, including light intensity
Follow standard checklist, SOPs
and maintain a record of job completion.
Commissioning of Instrumentation Systems
Check for loop and logic test
according to cause and effect diagram.
Conduct non-operating checks to
ensure instrument operability. This must be done by removing all shipping stops,
check pointer travels and verifying the instrument capability to measure,
operate, and stroke in the direction and manner required by the process
application.
Instruments must be bench or
field calibrated with standard test equipment/ media according to clients or
manufacturer instructions. Ensure all required adjustments and control point
settings is done and recorded.
Ensure that the SS piping/
tubing from instruments to process piping is properly tightened.
Clean all transmission and
control tubing by blowing with cooled and filtered clean air before connecting
to instrument components.
Clean all air-supply headers by
blowing with clean air and check them for tightness.
Perform leak test of pneumatic
control circuits in accordance with the applicable standards.
Ensure proper installation and
connections of all system components by verifying their conformance with data
sheets, drawings and specifications. Function test should be checked by using
dummy transmission signals or by shorting the terminals to verify the design intend/
criteria.
Check all electrical signals
and alarm wiring for continuity, correct source of power, and polarity.
Check thermocouples for proper
joining of wires, position of elements in thermowells, proper polarity, and
continuity of receiving instruments.
Ensure correct tagging is
available on each instrument and connections. Tagging must be ensured on orifice
plates for ease of identification.
Orifice plate must be installed
after completion of flushing operations only. Check and record the bores of
orifice plates.
Isolate or remove, if
necessary, inline components such as control valves, positive displacement
meters, and turbine meters for pressure testing. Reinstall these items after
testing the system with the components removed or isolated.
Isolate or remove components
for flushing operations and reinstall them on the completion.
Install any sealing fluids, as
required.
Fully pressurize and energize
the transmitting and control signal systems(s) by opening process connections
at primary sensors and final regulators and by making control mode settings for
automatic operation of equipment as the process unit is charged and bought on
stream.
Make a schedule of recording of
required parameter.
Commissioning
of DCS/ESD/PLC/MMS
System
Check the proper installation
of DCS/ESD/PLC Panels and inside components as per drawing and data sheets.
Check and connect the panel and
instrument earthlings at proper places.
Check the IR values for
individual cores of power and instrument cables.
Loop checking for all the
instrument and power connections.
Connect all the cable to proper
terminal blocks inside system panels.
Check and connect the network
cables from system to corresponding consoles.
Power up and install the HMI.
Power up the cabinets and
ensure the reading of all input signals to DCS/ESD/PLC.
Check output signal from the
system.
Check the interface.
Proceed for final loop checking
and calibrations as per site acceptance test procedure.
Commissioning activities for vessels
Inspect the vessel internally before
and after installation as per defined scope.
Check all instrumentation
including PT, FT, LT, SRV, BV, etc.
Flush/ Dry out and install
material that are desired.
Ensure the compliances of all
statutory requirement.
Review the blind register and
boxup after proper execution of work permits.
Ensure tagging and marking of
vessel with all fittings.
Ensure the plugging or blinding
of open drain points.
Commissioning
activities for fired
heaters
Perform all non-operating pre
firing checks in accordance with the manufacturer’s instructions and checklist.
Perform the pressure test in
accordance with the applicable codes, specifications and the client’s
instructions.
Check operation of dampers and
verify position of indicators.
Check operation of air
preheaters, blowers.
Ensure the cleanliness of fuel
lines by performing blowing operation and then connect burner pipes.
Dry refractories during initial
firing by following the manufacture’s temperature cycles.
Conduct boil out, chemical
cleaning, and flushing operations as desired. Ensure safe disposal of wastes
and cleaning media in accordance with the established procedure.
Conduct light off, drying, and
purging operations.
Get the assistance of OEM or Licensor’s
for technical advice during installation, commissioning or start-up, if desired
Commissioning activities for pumps, compressors and drivers
Ensure that level base plate,
sole plates and grout all bearing surfaces are acceptable .
Lighten any excess piping
stresses that may be imposed on pumps, compressors, and drivers.
Clean complete lube oil system.
Charge the lube oil, seal oil,
and oil cooling system with flushing oil system and circulate for cleaning
purposes.
Charge the lube oil, seal oil
and oil cooling system with the operating oil recommended by the manufacturer.
Cold testing of overload
protection and trip logic actuation/delay timer etc.
Operate equipment and monitor
for checking vibration, temperature, trip, governor functioning and other
safety device.
Checks for any operating tests
and adjustments, as required.
Get assistance of OEM’s service
engineer for technical advice during installation or commissioning, if
required.
Maintain records
Commissioning of Urea conveyer system
Check for proper alignment
between motor and drive pulley.
Check for functioning of pull
chord.
Check for operation conveyor
belt limit switch for its sideways movement.
Check for proper tensioning in
conveyor belt.
Check for conveyor belt joint.
Check the availability of
machine guards.
Check the obstacle free
platform around the conveyor belt.
Check the function of start-up
hooter.
Fill the checklist and OEM instructions.
Commissioning of Storage tanks
Perform leak test/ hydro test
according to standard specification.
Disposal of test water must be
done in accordance with client guideline.
Conduct chemical cleaning and
flushing operations, as required. Dispose out wastes and cleaning media in
accordance with established procedure.
Perform dry out activity as
required.
Witness test and inspections to
extent desired.
Ensure standard tagging of
tanks.
Follow permit to work for safe
execution of the job.
Commissioning of piping system
All piping must be hydrostatically
or pneumatically tested according to specifications and types of services.
Commissioning team must witness
field pressure test.
Flush and drain the system
properly and install the orifice plate. (Orifice plate should not be installed
before hydrostatic testing)
The system should be drained
properly, remove blinds, and perform tightness test.
After completion of test,
piping and fittings can be insulate or painted. Ensure proper painting of
welded joints as per standards.
All welded joints such as longitudinal,
girth, and nozzle of underground piping that have not been shop tested shall be
left exposed (free from paint, drop, and wrap) until the specified testing has
been completed and accepted by client. Piping can be covered or backfilled after
final testing of the joints.
Check pipe-hangers, support,
guide, expansion joints, and other pipe specialities for the removal of all
shipping and erection temporary items.
Identify the requirement for
cold and hot tightening of bolts for the designed services. There should be
clear instructions for hot setting expansion joints.
Check for pipe-hangers support,
guides, and pipe specification for hot settings. If requires, make minor
adjustment for system safety.
As specified in data sheet and
system specifications, install permanent filter elements.
During commissioning stage,
identify and record the support vibration and thermal expansion problem and
rectify it immediately.
Ensure proper torque of bolts
for both cold and hot services. Re-torque all hot and cold service bolting
during commissioning and start-up, if demand.
Commissioning activities - Water Treatment Plants
Follow the commissioning
checklist for readiness of system
Ensure completeness and
correctness of installations as per drawing and make any non-operating checks
that may be required.
Provide and install the initial
charge of ion-exchange resins and inert bed material.
Arrange all water treatment
chemicals except the initial charge resins.
Make the necessary operating
tests and adjustments to water treatment systems.
Obtain the services of a water
consultant to advise and monitor the water treatment operation, as required by
the Owner.
Ensure readiness of potable
water, service water, drinking water systems.
Commissioning activities for Cooling Towers and Fire Water Systems
Inspect for completeness and
correctness of installations and make any non-operation checks that may be
required.
Clean the cooling tower basin and install
screens in the suction pit before water circulation.
Flush, drain, and clean the
cooling tower basins.
Clean intake screens.
Adjust cooling tower fans to
obtain specified tip clearance and test.
Operate fire pumps to check performance of
systems.
Vessels, tanks and other water
system equipment as required, fill with water, check for leaks and flush to
clean.
Arrange for insurance company
inspection of the fire system as required.
Obtain and install all required
fire- fighting chemicals and portable equipment such as hoses, fire
extinguishers and related equipment.
Establish the water treatment
program.
Obtain the services of a water
consultant to advise and monitor the water treatment as required.
Commissioning activities for Boilers
Inform IBR inspector in advance
Make a non-operating boiler
pressure test in accordance with applicable codes, specifications.
Inspect the boiler for
completeness and correctness of installation and make other non-operating
pre-firing checks.
Check operation of FD fan,
scanner fan, and other equipment for proper operations.
Dry refractories during initial
firing by following the manufacturer’s temperature cycles.
Purge, flush, and drain steam
mains, as necessary.
Obtain and charge treated water
for bailout and initial operation, as required.
Commission auxiliaries as
detailed elsewhere under the appropriate equipment type.
Conduct boil out, chemical
cleaning, and flushing operation, as required. Dispose of wastes and cleaning
media in accordance with the established procedure.
Obtain the assistance of OEM’s service
engineer for technical advice during installation or start-up, if desired.
Conduct all operating tests and
obtain the required certification.
Recheck and set pressure-relief
valves.
Maintain relevant records for
future use.
Commissioning activities – Catalyst and chemical Loading
Inspect the vessel internally
for cleanliness, completeness, and proper installation of internal fittings.
Check location and length of
instruments.
Check location and fabrication
details of distributor piping and internal trays.
Check range of level instrument
floats or outside floats cage connection.
Commissioning activities for Waste Disposal system
Inspect facilities for its completeness
and correctness of installation and make any non-operating checks to ensure
their conformance to specifications.
Operate all equipment and
arrange all chemicals and agents related to waste treatment.
Obtain the services of a waste
treatment consultant to advise and monitor the system operation as required.
Commissioning activities for Building and Accessories
Check installation including
HVAC equipment to ensure their completeness and conformance to specifications
As required, obtain
certification that all plumbing, electrical, fire protection, elevator and
special materials handling installations canopy with government regulations.
Operate HVAC unit and make all
performance tests.
Conclusion
Pre-commissioning and
commissioning activities should be prepared after
detail discussion and brain storming with highly experience team members who have
served in major fertilizer companies. Various codes, published
articles and case studies should be referred finalizing commissioning
activities and preparing commissioning checklists
Safety should be a high
priority when performing any activity related to the commissioning of the
ammonia urea plant.
You may find affiliate
links in this article. This means that if you click on a link and purchase any
of the products on this page, we may receive a commission, at no additional
cost to you, It does not affect our knowledge sharing, opinions or reviews. Everything
we do is benefit for you as the reader, so all our knowledge sharing, reviews
are as honest and unbiased as possible.
No comments
Please don't add links in the comments, they will be treated as spam comments